INDUSTRIAL BUILDINGS |
EXTRACTION AND REFINING OF COOKING OILS |
![]() ![]() |
NEFERTITI | |||||
|
||||||
| This
complex consists of a preparation unit that is linked to a solvent
extraction unit.
It has a daily capacity of 400 tonnes of soya grains or 200 tonnes of cotton grains and has a complete refinery which treats locally produced or imported oil at a rate of 200 tonnes daily. The peripheral equipment used is made up essentially of grain silos (up to 20,000 tonnes), different oil storage tanks, cooling towers, steam and compressed air production, electricity supply, water treatment, a fire protection system, a laboratory and a workshop. |
![]() |
ROUEN | |||||
|
||||||
| Extraction of vegetable oil using complete automation system. |
| BEJAIA | ||||||
|
||||||
| One of the largest oilseed crushing complexes ever built by any one constructor on behalf of the Entreprise Nationale des Corps Gras, located 300 km from Algiers. TCA, which provided the advisory engineers for the civil engineering work, carried out the engineering study and design work for the 11 buildings with steel frames which now refine and bottle 400 tonnes of food oil on a daily basis. |
| DAMMAM | ||||||
|
||||||
| Complete refining and oil bottling. |
| JEDDAH | ||||||
|
||||||
| A new ‘winterization’ unit within an existing factory. |
![]() |
MANAMA | |||||
|
||||||
| An integrated oilseed crushing complex made up of a refinery unit, a bottling unit and, in addition, a metallic box manufacturing unit together with roads, tracks and a transfer rack between the factory and the port located three kilometres away. |
| SALZGITTER | ||||||
|
||||||
| A refinery. |
![]() |
DAKAR | |||||
|
||||||
| A refinery. |
![]() |
HODEIDAH | |||||
|
||||||
| A complete refinery with operative buildings and port storage. |
| OWERRI | ||||||
|
||||||
| A palm oil refinery with packaging of the oil. |
![]() |
SOGUIPA | |||||
|
||||||
| A palm oil seed crushing unit complete with a water purification station. |
| MOMBASA | ||||||
|
||||||
| In this case, TCA was responsible for the design engineering and drawing up the construction plans for the concrete and metallic frame for a highly comprehensive preparation and extraction factory dealing with 600 tonnes of soya per day as well as for the flour treatment, utilities and important storage silos. |
| ANCONA | ||||||
|
||||||
| The renovation and installation of new extraction installations within an existing factory under particularly difficult construction conditions whereby the number of interruptions to production had to be kept to an minimum. |
| PORT OF SPAIN | ||||||
|
||||||
| A complete extraction factory. |
THE SOAP INDUSTRY |
| OWERRI | ||||||
|
||||||
| BEJAIA | ||||||
|
||||||
| ENCG
wanted to install a new unit within its Bejaia complex that would produce
150 tonnes of household soap and 50 tonnes of packaged toilet soap daily.
Of course, it entrusted De Smet with the completion of this project, which
in turn called upon the support of Mazzoni.
TCA was entrusted with the task of drawing up project specifications relating to the civil engineering work which involved, over and above the production buildings, several additional buildings including a soda dissolution unit, large storage areas, roads, tracks and transfer racks. TCA was present on-site to a considerable extent and participated above all in preparing and obtaining the necessary agreements from the various local authorities, in particular as regards the technical checks on the construction work. |
STARCH PLANTS |
| ALEXANDRIE | ||||||
|
||||||
| An integrated starch and starch derivatives production complex. |
| KHARTOUM | ||||||
|
||||||
| An integrated starch and starch derivatives production complex. |
SUGAR PLANTS |
| WANZE 2 | ||||||
|
||||||
![]() |
LA SUCRERIE DU MOSO | |||||
|
||||||
| PERLEUR | ||||||
|
||||||
| WANZE | ||||||
|
||||||
| The Tirlemont group decided to take advantage of the time available between the beetroot seasons and entrusted De Smet and TCA with the reconstruction of this new workshop which was ready for use in time for the start of the sugar season in September 1996 in spite of all sorts of unforeseen difficulties due to the fact that this building is over 200 years old! |
CEMENT PLANT |
| QASSIM | ||||||
|
||||||
| We designed the largest building involved in the project to extend the QASSIM CEMENT COMPANY cement plant, that being the "Preheater Tower", a 62-metre-high tower built on a 7 m concrete infrastructure housing the electricity units. The area of this building, which was calculated in accordance with seismic levels and the German DIN standards, covers an area of only 14 m by 16 m. It has 6 intermediary mixed platforms and comprises in excess of 400 tonnes of reconstituted soldered sections. |
BREWERIES |
![]() |
ANNABA | |||||
|
||||||
![]() |
BAIA MARE | |||||
|
||||||
| This project involved the renovation of an existing brewery and the addition of a new bottling room. All of this was to take place within a seismic environment and a highly demanding administrative and legal context. The project, that was carried out by Interbrew, was completed within slightly less than a year in Baia Mare in the Carpathians. Even vampires appreciate our Belgian calculations, engineering, equipment ... and beer! |
WATER TREATMENT |
![]() |
SÈTE | |||||
|
||||||
| SÈTE | ||||||
|
||||||
| SÈTE | ||||||
|
||||||
| SÈTE | ||||||
|
||||||
WOOL SCOURING |
| AUSTRALIA | ||||||
|
||||||
| TAIWAN | ||||||
|
||||||
WATER TOWER |
| In Cameroon, TCA drew up the calculations and designs for more than 30 water tanks for the CFE and for BESIX |
SLAUGHTERHOUSES |
POWER PLANTS |
WAREHOUSES |
High voltage / Low voltage ELECTRICAL CAGES |
RACKS |
SEMI-INDUSTRIAL BUILDINGS |
| TGV | |
| Study
on works of art along the TGV route between the N 60 road and the Arbre
viaduct.
This stretch is made up of 9 lower passages and 5 upper passages in pre-stressed reinforced concrete. The lower passages are of the frame or portal type, whilst the upper passages have one or three pre-stressed concrete apron spans. |
| SNCB/CIBE | |
| Pedestrian gallery. Push piling. 30 metres long, diameter 2 to 7 metres deep |
| ST DENIS | ||||||||
|
||||||||
| SPORTS HALL - HAREN | |
| Sports hall for the City of Brussels |
| SPORTS HALL - PAVIE | |
| Sports hall for the City of Brussels |
| ENTRANCE HALL | |
| BRUPARK - Brussels |
| SPARE PARTS STORE | |
| RENAULT - Mechelen |
| TRANSPORTERS & GANTRY CRANE | |
| SOLVAY - Antwerp (Port) |
| INDUSTRIAL HALL | |
| PETITE ILE -
Brussels Sportco SA |
| MOBILE TELEPHONE PYLONS | |
| MOBISTAR |
| WAREHOUSES AND ADMINISTRATIVE COMPLEXES | |
| ROYALE BELGE |